IT専門者になりたいの夢

http://www.pass4test.jp

PK0-003技術試験、N10-005学習指導

NO.1 Two employees will not work on the same project together. The project manager tells the employees totalk to their supervisors because the supervisors recommended they work together.This is an example of which of the following conflict resolution styles?A. WithdrawingB. ForcingC. AcceptingD. CompromisingAnswer: BCompTIA基礎問題集PK0-003受験料NO.2 A project manager notices that status meetings are poorly attended and that one or two team membertry to dominate the meetings. Which of [...]